[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121167":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1121167,790,1,"单选题","后浇带通常根据设计要求留设，至少保留（ ）d后再浇筑，将结构连成整体。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","28","2021\u002F2020版教材P69 七、后浇带的设置与处理，后浇带通常根据设计要求留设，并保留一段时间（若设计无要求，则至少保留14d并经设计确认）后再浇筑，将结构连成整体。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]