[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121144":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1121144,790,1,"单选题","设有钢筋混凝土构造柱的抗震多层砖房，其施工顺序应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","先绑扎钢筋，然后浇筑混凝土构造柱，最后砌砖墙",false,{"key":16,"text":17,"correct":14},"B","先砌砖墙，然后绑扎钢筋，最后浇筑混凝土构造柱",{"key":19,"text":20,"correct":14},"C","先浇筑混凝土构造柱，然后绑扎钢筋，最后砌砖墙",{"key":22,"text":23,"correct":24},"D","先绑扎钢筋，然后砌砖墙，最后浇筑混凝土构造柱",true,"2021\u002F2020版教材P74 （15） 设有钢筋混凝土构造柱的抗震多层砖房， 应先绑扎钢筋，然后砌砖墙，最后浇筑混凝土。墙与柱应沿髙度方向每500mm 设料6 拉筋一砖墙）， 每边伸入墙内不应少于lm; 构造柱应与圈梁连接； 砖墙应砌成马牙槎，每一马牙槎沿髙度方向的尺寸不趄过300mm， 马牙槎从每层柱脚开始，先退后进。该层构造柱混凝土浇筑完以后，才能进行上一层施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]