[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1121134,790,1,"单选题","关于模板拆除的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","底模及其支架拆除应符合设计或规范要求",false,{"key":16,"text":17,"correct":18},"B","后张法预应力构件侧模宜在预应力张拉前拆除",true,{"key":20,"text":21,"correct":14},"C","后张法预应力构件底模宜在预应力张拉前拆除",{"key":23,"text":24,"correct":14},"D","拆模通常先拆承重部分后拆非承重部分","2021\u002F2020版教材P62 （1） 模板拆除时，拆模的顺序和方法应按模板的设计规定进行。当设计有规定时，可 采取先支的后拆、后支的先拆，先拆非承重模板、后拆承重模板的顺序，并应从上而下进 行拆除。（2）当混凝土强度达到设计要求时，方可拆除底模及支架；当设计无具体要求时，同条件养护试件的混凝土抗压强度应符合表2A312031的规定。A不准确。（3） 当混凝土强度能保证其表面及棱角不受损伤时，方可拆除侧模。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]