[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121124":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1121124,790,2,"多选题","关于通常情况下模板拆除顺序的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先支先拆，后支后拆",false,{"key":16,"text":17,"correct":18},"B","后支先拆，先支后拆",true,{"key":20,"text":21,"correct":18},"C","先拆非承重部分，后拆承重部分",{"key":23,"text":24,"correct":14},"D","先拆承重部分，后拆非承重部分",{"key":26,"text":27,"correct":14},"E","先下后上，先内后外","BC","2021\u002F2020版教材P62 （1） 模板拆除时，拆模的顺序和方法应按模板的设计规定进行。当设计尤规定时，可 采取先支的后拆、后支的先拆，先拆非承重模板、后拆承重模板的顺序，并应从上而下进 行拆除。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]