[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121103":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1121103,790,2,"多选题","降水井井点管安装完毕后应进行试运转，全面检查( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","管路接头",true,{"key":16,"text":17,"correct":14},"B","出水状况",{"key":19,"text":20,"correct":21},"C","观测孔中的水位",false,{"key":23,"text":24,"correct":21},"D","排水沟",{"key":26,"text":27,"correct":14},"E","机械设备运转情况","ABE","2021\u002F2020版教材P52 （4）井点管安装完毕应进行试运转，全面检查管路接头，出水状况和机械设备运转情况",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]