[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121086":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1121086,790,2,"多选题","验槽应重点观察( )部位。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","柱基",true,{"key":16,"text":17,"correct":14},"B","墙角",{"key":19,"text":20,"correct":14},"C","承重墙",{"key":22,"text":23,"correct":14},"D","受力较大部位",{"key":25,"text":26,"correct":27},"E","受力较小部位",false,"ABCD","2021\u002F2020版教材P54 (1)槽壁、槽底的土质情况，验证基槽开挖深度，初步验证基槽底部土质是否与勘察报告相符，观察槽底土质结构是否受到人为破坏；验槽时应重点观察柱基、墙角、承重墙下或其他受力较大部位，如有异常部位，要会同勘察、设计等有关单位进行处理。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]