[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121081":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1121081,790,2,"多选题","基坑验槽时,先由施工単位进行自检,然后由( )组织相关単位进行验槽。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设単位项目负责人",true,{"key":16,"text":17,"correct":18},"B","勘察单位",false,{"key":20,"text":21,"correct":18},"C","设计単位项目负责人",{"key":23,"text":24,"correct":18},"D","施工单位项目负责人",{"key":26,"text":27,"correct":14},"E","总监理工程师","AE","2021\u002F2020版教材P53 此题考核基坑验槽。对于验槽主要研究验槽资料、验槽程序、验槽方法、局部不良地基的处理。基坑验槽时,,先由施工单位进行自检,然后由总监理工程师或建设单位项目负责人组织建设、监理、勘察、设计及施工单位的项目负责人、技术质量负责人,共同按设计要求和有关规定进行。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]