[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121072":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1121072,790,2,"多选题","基坑(槽)施工方案的主要内容包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","现场环境",false,{"key":16,"text":17,"correct":18},"B","分层开挖深度",true,{"key":20,"text":21,"correct":18},"C","开挖时间及顺序",{"key":23,"text":24,"correct":18},"D","支护结构设计",{"key":26,"text":27,"correct":18},"E","降水措施及监测要求","BCDE","2021\u002F2020版教材P53 四、验槽的主要内容：（1）根据设计图纸检查基槽的开挖平面位置、尺寸、槽底深度，检查是否与设计图纸相符，开挖深度是否符合设计要求；（2）仔细观察槽壁、槽底土质类型、均匀程度和有关异常土质是否存在，核对基坑土质及地下水情况是否与勘察报告相符；（3）检查基槽之中是否有旧建筑物基础、古井、古墓、洞穴、地下掩埋物及地下人防工程等；（4）检查基槽边坡外缘与附近建筑物的距离，基坑开完对建筑物稳定是否有影响；（5）天然地基验槽应检查核实分析钎探资料，对存在的异常点位进行复合检查、桩基应检测桩的质量合格。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]