[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121071":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1121071,790,2,"多选题","地下水的控制方法包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","集水明排",true,{"key":16,"text":17,"correct":14},"B","真空井点降水",{"key":19,"text":20,"correct":14},"C","喷射井点降水",{"key":22,"text":23,"correct":14},"D","管井降水",{"key":25,"text":26,"correct":27},"E","人工式降水",false,"ABCD","2021\u002F2020版教材P52 一、明沟、集水排水；二、降水降水即在基坑土方开挖之前，用真真空（轻型）井点降水、喷射井点降水或管深入含水层内，用不断抽水的方式使地下水位下降至基坑底以下，同时使土体产生固结以方便土方开挖。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]