[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121068":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1121068,790,2,"多选题","关于大体积混凝土裂缝控制做法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","控制混凝土入模温度",true,{"key":16,"text":17,"correct":18},"B","增大水灰比,加大水泥用量",false,{"key":20,"text":21,"correct":18},"C","混凝土浇筑完毕，无需覆盖",{"key":23,"text":24,"correct":14},"D","掺入适量微膨胀剂",{"key":26,"text":27,"correct":14},"E","可在基础内部预埋冷却水管，通入循环冷却水，强制降低混凝土水化热温度","ADE","2021\u002F2020版教材P57 (1)优先选用低水化热的矿渣水泥拌制混凝土，并适当使用缓凝减水剂(2)在保证混凝土设计强度等级前提下，适当降低水灰比，减少水泥用量(3)降低混凝土的入模温度，控制混凝土内外的温差(当设计无要求时，控制在25℃以内)(4)及时对混凝土覆盖保温、保湿材料(5)可在基础内部预埋冷却水管，通入循环冷却水，强制降低混凝土水化热温度(6)在拌和混凝土时，还可掺入适量合适的微膨胀剂或膨胀水泥，使混凝土得到补偿收缩，减少混凝土的温度应力(7)设置后浇缝。当大体积混凝土平面尺寸过大时，可以适当设置后浇缝，以减小外应力和温度应力；同时，也有利于散热，降低混凝土的内部温度(8)大体积混凝土必须进行二次抹面工作，减少表面收缩裂缝。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]