[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1121044,790,1,"单选题","验槽时，应重点观察( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基坑中心点",false,{"key":16,"text":17,"correct":14},"B","基坑边角处",{"key":19,"text":20,"correct":21},"C","受力较大的部位",true,{"key":23,"text":24,"correct":14},"D","最后开挖的部位","2021\u002F2020版教材P54 观察法(1)槽壁、槽底的土质情况，验证基槽开挖深度，初步验证基槽底部土质是否与勘察报告相符，观察槽底土质结构是否受到人为破坏;验槽时应重点观察柱基、墙角、承重墙下或其他受力较大部位，如有异常部位，要会同勘察、设计等有关单位进行处理。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]