[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1121017":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1121017,790,1,"单选题","对于条形基础浇筑，以下说法不正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","混凝土宜分段分层连续浇筑，不留施工缝",false,{"key":16,"text":17,"correct":14},"B","混凝土分段浇筑时，每段浇筑长度控制在2000～3000mm",{"key":19,"text":20,"correct":21},"C","采用原槽土模时，应在基槽两侧的土壁上交错打入长100mm左右的标杆，并露出10—20mm",true,{"key":23,"text":24,"correct":14},"D","逐段逐层呈阶梯形向前推进","2021\u002F2020版教材P57 根据基础深度宜分段分层连续浇筑混凝土，一般不留施工缝。各段层间应相互衔接，每段间浇筑长度控制在20003000mm距离，做到逐段逐层呈阶梯形向前推进。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]