[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120999":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1120999,790,1,"单选题","采用平碾压实土方时，每层虚铺厚度为( )，每层压实遍数为( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","200～250mm,3～4遍",false,{"key":16,"text":17,"correct":14},"B","200～250mm,6～8遍",{"key":19,"text":20,"correct":14},"C","250～300mm,3～4遍",{"key":22,"text":23,"correct":24},"D","250～300mm,6～8遍",true,"2021\u002F2020版教材P51 表2A312021，采用平碾压实土方时，每层虚铺厚度为250~300MM，每层压实遍数6~8遍。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]