[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120997":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120997,790,2,"多选题","下列属于验槽前的准备工作的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","察看结构说明和地质勘查报告，对比结构设计所用的地基承载力、持力层与报告所提供的是否相同。",true,{"key":16,"text":17,"correct":14},"B","询问、察看建筑位置是否与勘察范围相符",{"key":19,"text":20,"correct":21},"C","察看开挖方法是否与专项方案相同",false,{"key":23,"text":24,"correct":14},"D","察看场地内是否有软弱下卧层",{"key":26,"text":27,"correct":21},"E","要求建设方提供场地外是否有地下管线和相应地下设施","ABD","2021\u002F2020版教材P53 二、验槽前的准备工作(1)察看结构说明和地质勘察报告，对比结构设计所用的地基承载力、持力层与报告所提供的是否相同；(2)询问、察看建筑位置是否与勘察范围相符；(3)察看场地内是否有软弱下卧层；(4)场地是否为特别的不均匀场地、是否存在勘察方要求进行特别处理的怙况，而设计方没在进行处理；(5)要求建设方提供场地内是否有地下管线和相应的地下设施。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]