[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120996":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120996,790,2,"多选题","钻孔灌注桩泥浆护壁成孔的工艺中，“清孔”前的工序包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","埋没护筒",true,{"key":16,"text":17,"correct":14},"B","成孔",{"key":19,"text":20,"correct":14},"C","预备泥浆",{"key":22,"text":23,"correct":24},"D","下钢筋笼",false,{"key":26,"text":27,"correct":24},"E","浇筑混凝土","ABC","2021\u002F2020版教材P58 泥浆护壁法钻孔灌注粧施工工艺流程：场地平整—粧位放线—开挖浆池、浆沟—护筒埋设—钻机就位、孔位校正—成孔、泥桨循环、清除废浆、泥渣—第一次清孔—质量验收—下钢筋笼和钢导管—第二次清孔—浇筑水下混凝土—成桩。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]