[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120991":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120991,790,2,"多选题","基坑开挖时，应对( )等经常复测检查。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","平面控制桩",true,{"key":16,"text":17,"correct":14},"B","水准点",{"key":19,"text":20,"correct":14},"C","基坑平面位置",{"key":22,"text":23,"correct":14},"D","水平标高",{"key":25,"text":26,"correct":27},"E","支撑形式",false,"ABCD","2021\u002F2020版教材P51 (12)开挖时应对平面控制桩、水准点、基坑平面位置、水平标高、边坡坡度等经常进行检查。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]