[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120984":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1120984,790,1,"单选题","土方回填土工程施工技术要求中，当回填土场地陡于( )时，应先将斜坡挖成阶梯形，然后分层填土，以利结合和防止滑动。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1\u002F3",false,{"key":16,"text":17,"correct":18},"B","1\u002F5",true,{"key":20,"text":21,"correct":14},"C","1\u002F6",{"key":23,"text":24,"correct":14},"D","1\u002F4","2021\u002F2020版教材P51 清除基底垃圾、草皮、杂物时，应采取措施防止地表滞水流入填方区，浸泡地基，造成基土下陷，当填土场地地面陡于1\u002F5时，应先将斜坡挖成梯形，阶高0.2～0.3m，阶宽大于1m，然后分层填土，以利结合和防止滑动。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]