[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120982":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120982,790,2,"多选题","基坑开挖前，应根据( )、施工方法、施工工期和地面荷载等资料，制定基坑施工方案。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","支护结构形式",true,{"key":16,"text":17,"correct":14},"B","基坑深度",{"key":19,"text":20,"correct":14},"C","地质条件",{"key":22,"text":23,"correct":14},"D","周围环境",{"key":25,"text":26,"correct":27},"E","地基承载力",false,"ABCD","2021\u002F2020版教材P50 土方开挖(1)开挖前，应根据支护结构形式、挖深、水文地质条件、施工方法、周围环境、工期、气候、地面载荷和危险源等资料制定施工安全方案，经审批后严格按照方案实施。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]