[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120979":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120979,790,2,"多选题","在深基坑工程的挖土方案中，主要的挖土方案包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","放坡挖土",true,{"key":16,"text":17,"correct":14},"B","中心岛(墩)式挖土",{"key":19,"text":20,"correct":21},"C","斜坡挖土",false,{"key":23,"text":24,"correct":14},"D","逆作法挖土",{"key":26,"text":27,"correct":14},"E","盆式挖土","ABDE","2021\u002F2020版教材P50 (4)无支护土方工程采用放坡挖土，有支护土方工程可采用中心岛式（也称墩式）挖土、盆式挖土和逆作法挖土等方法。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]