[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120977":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120977,790,2,"多选题","符合深基坑开挖要求的表述是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","土方开挖顺序必须与支护结构的设计工况严格一致",true,{"key":16,"text":17,"correct":14},"B","盆式挖土是先开挖基坑中间部分的土，周围四边留土坡，土坡最后挖除",{"key":19,"text":20,"correct":21},"C","深基坑工程的挖土方案主要有放坡挖土、中心岛式（也称墩式）挖土、盆式挖土和逆作法挖土，四种方案皆有支护结构",false,{"key":23,"text":24,"correct":14},"D","开挖时应对平面控制桩、水准点、基坑平面位置、水平标高、边坡坡度等经常进行检查",{"key":26,"text":27,"correct":14},"E","当基坑较深，地下水位较高，开挖水位较高，开挖土体大多位于地下水位以下时，应采取合理的人工降水措施","ABDE","2021\u002F2020版教材P50 （4）无支护土方工程采用放坡挖土，有支护土方工程可采用中心岛式挖土、盆式挖土和逆作法挖土等方法。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]