[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120974":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120974,790,2,"多选题","基坑水平和竖向位移监测点应沿基坑周边布置，并符合以下规定( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","周边中部、阳角处应布置监测点",true,{"key":16,"text":17,"correct":18},"B","监测点水平间距不宜大于25m",false,{"key":20,"text":21,"correct":18},"C","每边监测点数不宜少于2个",{"key":23,"text":24,"correct":14},"D","水平和竖向监测点宜为共用点",{"key":26,"text":27,"correct":14},"E","监测点宜设置在围护墙或基坑坡顶上","ADE","2021\u002F2020版教材P59 （4）基坑围护墙或基坑边坡顶部的水平和竖向位移监测点应沿基坑周边布置，周边中部、阳角处应布置监测点，监测点的水平间距不宜大于15~20m，每边监测点数不宜少于3个，水平和竖向监测点宜为共用点，监测点宜设置在围护墙或基坑坡顶上",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]