[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120967":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120967,790,2,"多选题","结构施工期间测量的主要工作内容有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","轴线基准点设置",true,{"key":16,"text":17,"correct":14},"B","施工楼层放线抄平",{"key":19,"text":20,"correct":14},"C","轴线投测",{"key":22,"text":23,"correct":14},"D","标高传递",{"key":25,"text":26,"correct":27},"E","测量人员培训",false,"ABCD","2021\u002F2020版教材P49 结构施工测量的主要内容包括：主轴线内控基准点的设置、施工层的放线与抄平、建筑物主轴线的竖向投测、施工层标高的竖向传递等。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]