[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120962":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120962,790,2,"多选题","施工测量现场的主要工作有对( )的测设。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","长度",true,{"key":16,"text":17,"correct":14},"B","角度",{"key":19,"text":20,"correct":14},"C","平面位置",{"key":22,"text":23,"correct":14},"D","高程",{"key":25,"text":26,"correct":27},"E","城市水准点",false,"ABCD","2021\u002F2020版教材P48 施工测量现场的主要工作有，对已知长度的测设，已知角度的测设、建筑物细部点平面位置的测设、建筑物细部点高程位置及倾斜线的测设等。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]