[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120748":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1120748,790,1,"单选题","有抗震设防要求时，填充墙与框架之间宜采用( )的方法。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不脱开",false,{"key":16,"text":17,"correct":14},"B","半脱开",{"key":19,"text":20,"correct":21},"C","脱开",true,{"key":23,"text":24,"correct":14},"D","铰接","2021\u002F2020版教材P24 (8)填充墙与框架的连接，可根据设计要求采用脱开或不脱开方法。有抗震设防要求时宜采用填充墙与框架脱开的方法。当填充墙与框架采用脱开方法时，墙体高度超过4m时宜在墙髙中部设与柱连通的水平系梁，系梁的截面高度不小于60mm填充墙高不ft大于6m;当填充墙与框架采用不脱开方法时，填充墙长度超过5m或墙长大于2倍层高时，墙顶与梁宜有拉接措施，墙体中部应加设构造柱，墙高度超过4m吋允在墙高中部设置与柱连接的水平系梁，墙髙度超过6m时，宜沿墙髙每2m设置与柱连接的水平系梁，系梁的截面高度不小于60mm",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]