[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1120704,790,1,"单选题","砖混结构预制混凝土板与现浇板对接时，应满足( )的要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预制板端钢筋伸入现浇板中，后浇筑现浇板",true,{"key":16,"text":17,"correct":18},"B","现浇板钢筋伸入预制板缝中，先浇筑现浇板",false,{"key":20,"text":21,"correct":18},"C","预制板端钢筋伸入现浇板中，先浇筑现浇板",{"key":23,"text":24,"correct":18},"D","现浇板钢筋伸入预制板缝中，后浇筑现浇板","2021\u002F2020版教材P23页 3）预制混凝土板与现浇板对接时，预制板端钢筋应伸入现浇板中进行连接后，再浇筑现浇板。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]