[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120660":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1120660,790,1,"单选题","单位工程技术组织措施设计中不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","质量保证措施",false,{"key":16,"text":17,"correct":14},"B","安全保证措施",{"key":19,"text":20,"correct":14},"C","环境保护措施",{"key":22,"text":23,"correct":24},"D","资源供应保护措施",true,"2021\u002F2020版教材P18 施工组织设计原则：符合施工合同或招标文件有关进度、质量、安全、环境保护、造价等方面的要求；积极开发、使用新技术和新工艺，推广应用新材料新设备；坚持科学的施工程序和合理的施工顺序，采用流水施工和网络计划等方法，科学配置资源，合理布置现场，采取季节性施工措施，实现均衡施工，达到合理的经济指数指标；采取技术和管理措施，推广建筑节能和绿色施工；与质量、环境和职业健康安全三管理体系有效结合。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]