[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120385":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1120385,790,1,"单选题","冬季填方施工时，每层铺土厚度应比常温时（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加20～25%",false,{"key":16,"text":17,"correct":18},"B","减少20～25%",true,{"key":20,"text":21,"correct":14},"C","减少35～40%",{"key":23,"text":24,"correct":14},"D","增加35～40%","本题考查的是土方回填（冬期）。冬季填方每层铺土厚度应比常温施工时减少20%～25%（选项B），预留沉降量比常温时适当增加。土方中不得含冻土块及填土层受冻。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]