[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120382":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120382,790,2,"多选题","露天料场的搅拌站在雨后拌制混凝土时，应对配合比中原材料重量进行调整的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","水",true,{"key":16,"text":17,"correct":18},"B","水泥",false,{"key":20,"text":21,"correct":14},"C","石子",{"key":23,"text":24,"correct":14},"D","砂子",{"key":26,"text":27,"correct":18},"E","粉煤灰","ACD","本题考查的是混凝土工程（雨期）。雨期施工期间，对水泥和掺合料应采取防水和防潮措施，并应对粗、细骨料含水率实时监测，及时调整混凝土配合比。也就是调整水、石子、砂子的重量。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]