[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120376":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1120376,790,1,"单选题","下列暗龙骨吊顶工序的排序中，正确的是（ ）。 ①安装主龙骨；②安装副龙骨；③安装水电管线；④安装压条；⑤安装罩面板",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①③②④⑤",false,{"key":16,"text":17,"correct":14},"B","①②③④⑤",{"key":19,"text":20,"correct":21},"C","③①②⑤④",true,{"key":23,"text":24,"correct":14},"D","③②①④⑤","本题考查的是吊顶工艺流程。暗龙骨吊顶施工流程：放线→划龙骨分档线→安装水电管线→安装主龙骨→安装副龙骨→安装罩面板→安装压条。故正确答案是C。 吊顶工程应对下列隐蔽工程项目进行验收：（1）吊顶内管道、设备的安装及水管试压，风管的严密性检验；（2）木龙骨防火、防腐处理；（3）埋件；（4）吊杆安装；（5）龙骨安装；（6）填充材料的设置；（7）反支撑及钢结构转换层。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]