[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120362":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120362,790,2,"多选题","关于屋面防水工程的做法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","平屋面采用结构找坡，坡度2%",false,{"key":16,"text":17,"correct":18},"B","前后两遍的防水涂膜相互垂直涂布",true,{"key":20,"text":21,"correct":14},"C","上下层卷材相互垂直铺贴",{"key":23,"text":24,"correct":14},"D","采用先低跨后高跨、先近后远的次序铺贴连续多跨的屋面卷材",{"key":26,"text":27,"correct":18},"E","采用搭接法铺贴卷材","BE","本题考查的是屋面防水工程施工技术。混凝土结构层宜采用结构找坡，坡度不应小于3%。（选项A错误）。前后两遍的防水涂膜应相互垂直涂布，上下层卷材不得相互垂直铺贴。（选项B正确，选项C错误）。防水工程的成品保护考虑，当铺贴连续多跨的屋面卷材时，应按先高跨后低跨、先远后近的次序进行施工。（选项D错误）。铺贴卷材应采用搭接法，上下层及相邻两幅卷材的搭接缝应错开，搭接宽度应符合规范要求。（选项E正确）。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]