[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120336":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1120336,790,1,"单选题","关于模板拆除施工的做法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","跨度2m的双向板，混凝土强度达到设计要求的50%时，开始拆除底模",false,{"key":16,"text":17,"correct":18},"B","后张预应力混凝土结构底模在预应力张拉前拆除完毕",true,{"key":20,"text":21,"correct":14},"C","拆模申请手续经项目技术负责人批准后，开始拆模",{"key":23,"text":24,"correct":14},"D","模板设计无具体要求，先拆非承重的模板，后拆承重的模板","本题考查的是模板的拆除。跨度≤2m的板，拆除底模及支架时，其混凝土强度应大于等于设计强度的50%。选项A做法正确。对于后张预应力混凝土结构构件，侧模宜在预应力张拉前拆除；底模支架不应在结构构件建立预应力前拆除。选项B做法错误。拆模之前必须要办理拆模申请手续，在同条件养护试块强度记录达到规定要求时，技术负责人方可批准拆模。选项C做法正确。如果模板设计无具体要求时，可按先支的后拆，后支的先拆，先拆非承重的模板，后拆承重的模板及支架。选项D做法正确。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]