[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120309":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1120309,790,1,"单选题","某跨度6m、设计强度为C30的钢筋混凝土梁，其同条件养护试件（150mm立方体）抗压强度如下表，可拆除横梁底模的最早时间是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7d",false,{"key":16,"text":17,"correct":14},"B","9d",{"key":19,"text":20,"correct":21},"C","11d",true,{"key":23,"text":24,"correct":14},"D","13d","跨度6m的梁，同条件养护试件的混凝土抗压强度至少达到设计的混凝土立方体抗压强度标准值的75%时方可拆除底模，30*75%=22.5MPa，第11天符合要求。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]