[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120304":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1120304,790,1,"单选题","施工期间最高气温为25℃时，砌筑用普通水泥砂浆拌成后最迟必须在（）内使用完毕。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1h",false,{"key":16,"text":17,"correct":14},"B","2h",{"key":19,"text":20,"correct":21},"C","3h",true,{"key":23,"text":24,"correct":14},"D","4h","现场拌制的砂浆应随拌随用，拌制的砂浆应在3h内使用完毕；当施工期间最高气温超过30℃时，应在2h内使用完毕。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]