[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120301":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120301,790,2,"多选题","模板的拆除顺序一般为（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先支先拆，后支后拆",false,{"key":16,"text":17,"correct":18},"B","后支先拆，先支后拆",true,{"key":20,"text":21,"correct":18},"C","先拆非承重部分，后拆承重部分",{"key":23,"text":24,"correct":14},"D","先拆承重部分，后拆非承重部分",{"key":26,"text":27,"correct":14},"E","先下后上，先内后外","BC","模板拆除顺序：先支的后拆、后支的先拆，先拆非承重模板、后拆承重模板；",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]