[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120291":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120291,790,2,"多选题","关于钢筋混凝土预制桩锤击沉桩顺序的说法，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","基坑不大时，打桩可逐排打设",true,{"key":16,"text":17,"correct":14},"B","对于密集桩群，从中间开始分头向四周或两边对称施打",{"key":19,"text":20,"correct":14},"C","当一侧毗邻建筑物时，由毗邻建筑物处向另一方向施打",{"key":22,"text":23,"correct":24},"D","对基础标高不一的桩，宜先浅后深",false,{"key":26,"text":27,"correct":24},"E","对不同规格的桩，宜先小后大","ABC","本题考查的是混凝土预制桩施工技术。沉桩顺序应按先深后浅、先大后小、先长后短、先密后疏的次序进行（选项D、E）。对于密集桩群应控制沉桩速率，宜从中间向四周或两边对称施打；当一侧毗邻建筑物时，由毗邻建筑物处向另一方向施打。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]