[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120290":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1120290,790,1,"单选题","下列预应力混凝土管桩压桩的施工顺序中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先深后浅",true,{"key":16,"text":17,"correct":18},"B","先小后大",false,{"key":20,"text":21,"correct":18},"C","先短后长",{"key":23,"text":24,"correct":18},"D","自四周向中间进行","本题考查的是混凝土预制桩施工技术。预应力混凝土管桩的压桩顺序，其原则通常如下：根据基础的设计标高，宜先深后浅；根据桩的规格，宜先大后小、先长后短。根据桩的密集程度可采用自中间向两个方向对称进行；自中间向四周进行；由一侧向单一方向进行。选项A正确。选项B、C、D恰好表述相反。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]