[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120280":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120280,790,2,"多选题","关于土方开挖的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基坑开挖可采用机械直接开挖至基底标高",false,{"key":16,"text":17,"correct":18},"B","基坑开挖方案应根据支护结构设计、降排水要求确定",true,{"key":20,"text":21,"correct":18},"C","土方开挖前应先进行测量定位，设置好控制点",{"key":23,"text":24,"correct":18},"D","软土基坑必须分层均衡开挖",{"key":26,"text":27,"correct":18},"E","基坑开挖完成后应及时验槽，减少暴露时间","BCDE","机械挖土时，在接近设计坑底高程时应预留20～30cm厚的土层，用人工开挖和修坡，边挖边修坡，保证高程符合设计要求。超挖时，不准用松土回填到设计高程，应用砂、碎石或低强度混凝土填实至设计高程。选项A错误。挖土前，应预先设置轴线控制桩及水准点桩，并要定期进行复测和校验控制桩的位置和水准点标高。选项C正确。基坑开挖完成后，应及时清底、验槽，减少暴露时间，防止暴晒和雨水浸刷破坏地基土的原状结构。选项E正确。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]