[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120271":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1120271,790,1,"单选题","泥浆护壁钻孔灌注桩施工工艺流程中“第二次清孔”的下一道工序是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","下钢筋笼",false,{"key":16,"text":17,"correct":14},"B","下钢导管",{"key":19,"text":20,"correct":14},"C","质量验收",{"key":22,"text":23,"correct":24},"D","浇筑水下混凝土",true,"泥浆护壁法钻孔灌注桩施工工艺流程：场地平整→桩位放线→开挖浆池、浆沟→护筒埋设→钻机就位、孔位校正→成孔、泥浆循环、清除废浆、泥渣→第一次清孔→质量验收→下钢筋笼和钢导管→第二次清孔→浇筑水下混凝土→成桩。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]