[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120265":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1120265,790,1,"单选题","钢筋混凝土预制桩采用静力压桩法施工时，其施工工序包括:①打桩机就位；②测量定位；③吊桩、插桩；④桩身对中调直；⑤静压沉桩。一般的施工程序为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③④⑤",false,{"key":16,"text":17,"correct":18},"B","②①③④⑤",true,{"key":20,"text":21,"correct":14},"C","①②③⑤④",{"key":23,"text":24,"correct":14},"D","②①③⑤④","静力压桩法一般施工程序:测量定位→桩机就位→吊桩、插桩→桩身对中调直→静压沉桩→接桩→再静压沉桩→送桩→终止压桩→转移桩机。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]