[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120263":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120263,790,2,"多选题","基坑开挖完毕后，必须参加现场验槽并签署意见的单位有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","质监站",false,{"key":16,"text":17,"correct":18},"B","监理（建设）单位",true,{"key":20,"text":21,"correct":18},"C","设计单位",{"key":23,"text":24,"correct":18},"D","勘察单位",{"key":26,"text":27,"correct":18},"E","施工单位","BCDE","基坑验槽由总监理工程师或建设单位项目负责人组织建设、监理、勘察、设计及施工单位的项目负责人、技术质量负责人，共同按设计要求和有关规定进行。基槽满足设计要求及有关规定后，相关方履行验收手续。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]