[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120130":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120130,790,2,"多选题","施工现场的塔吊必须停止作业的天气状况有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","浮尘",false,{"key":16,"text":17,"correct":18},"B","大雨",true,{"key":20,"text":21,"correct":14},"C","大雪",{"key":23,"text":24,"correct":18},"D","大雾",{"key":26,"text":27,"correct":14},"E","五级大风","BD","本题考查的是垂直运输机械安全管理。遇六级及六级以上大风、大雨、雾等恶劣天气，应停止作业，将吊钩升起。行走式塔吊要夹好轨钳。雨雪过后，应先经过试吊，确认制动器灵敏可靠后方可进行作业。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]