[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120121":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120121,790,2,"多选题","关于塔吊安装、拆除的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","塔吊安装、拆除之前，应制定专项施工方案",true,{"key":16,"text":17,"correct":18},"B","安装和拆除塔吊的专业队伍可不具备相应资质，但需有类似施工经验",false,{"key":20,"text":21,"correct":14},"C","塔吊安装完毕，经验收合格，取得政府相关部门核发的《准用证》后方可使用",{"key":23,"text":24,"correct":14},"D","施工现场多塔作业，塔机间应保持安全距离",{"key":26,"text":27,"correct":18},"E","塔吊在六级大风中作业时，应减缓起吊速度","ACD","本题考查的是垂直运输机械安全管理。塔吊的安装和拆卸属特种作业，必须由取得相应资质的专业队伍进行，故B选项错误；遇六级及六级以上大风等恶劣天气，塔吊应停止作业，并将吊钩升起，行走式塔吊要夹好轨钳，故E选项错误。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]