[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120115":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1120115,790,1,"单选题","利用绿化代替场地硬化，属于绿色施工中的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","节材与材料资源利用",false,{"key":16,"text":17,"correct":18},"B","节地与施工用地保护",true,{"key":20,"text":21,"correct":14},"C","节能与能源利用",{"key":23,"text":24,"correct":14},"D","节水与水资源利用","本题考查的是绿色施工与新技术应用。选项A、C、D错误。最大限度地减少对土地的扰动，保护周边自然生态环境。红线外临时占地应尽量使用荒地、废地，少占用农田和耕地。利用和保护施工用地范围内原有的绿色植被。施工场地应硬化处理，有条件时，可对施工现场进行绿化布置。选项B说法正确，故正确答案是B。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]