[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120112":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120112,790,2,"多选题","项目施工过程中，应及时对“施工组织设计”进行修改或补充的情况有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","桩基的设计持力层变更",true,{"key":16,"text":17,"correct":14},"B","工期目标重大调整",{"key":19,"text":20,"correct":14},"C","现场增设三台塔吊",{"key":22,"text":23,"correct":14},"D","预制管桩改为钻孔灌注桩",{"key":25,"text":26,"correct":27},"E","更换劳务分包单位",false,"ABCD","本题考查的是施工组织设计的管理。项目施工过程中，发生以下情况之一时，施工组织设计应及时进行修改或补充：1）工程设计有重大修改；2）有关法律、法规、规范和标准实施、修订和废止；3）主要施工方法有重大调整；4）主要施工资源配置有重大调整；5）施工环境有重大改变。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]