[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120106":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120106,790,2,"多选题","基坑开挖完毕后，必须参加现场验槽并签署意见的单位有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","质监站",false,{"key":16,"text":17,"correct":18},"B","监理（建设）单位",true,{"key":20,"text":21,"correct":18},"C","设计单位",{"key":23,"text":24,"correct":18},"D","勘察单位",{"key":26,"text":27,"correct":18},"E","施工单位","BCDE","本题考查的是验槽程序。基坑开挖完毕后，应由建设单位（选项B）、设计单位（选项C）、勘察单位（选项D）、监理单位（选项B）、施工单位（选项E）等单位现场验槽，检查地基土与工程地质勘察报告、设计图纸是否相符，有无破坏原状土的结构或发生较大的扰动现象",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]