[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120103":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1120103,790,2,"多选题","分部工程验收可以由（ ）组织。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工单位项目经理",false,{"key":16,"text":17,"correct":18},"B","总监理工程师",true,{"key":20,"text":21,"correct":14},"C","专业监理工程师",{"key":23,"text":24,"correct":18},"D","建设单位项目负责人",{"key":26,"text":27,"correct":14},"E","建设单位项目专业技术负责人","BD","本题考查的是分部工程的质量验收。分部工程应由总监理工程师（选项B）或建设单位项目负责人（选项D）组织施工单位项目负责人和项目技术负责人等进行验收；勘察、设计单位项目负责人和施工单位技术、质量部门负责人应参加地基与基础分部工程的验收；设计单位项目负责人和施工单位技术、质量部门负责人应参加主体结构、节能分部工程的验收。",{"id":6,"name":31,"category":32,"favorite":33},"二建建筑工程实务","建筑工程",0]