[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120100":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1120100,790,1,"单选题","根据《建筑工程施工质量验收统一标准》（GB50300），单位工程竣工验收应由（ ）组织。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位（项目）负责人",true,{"key":16,"text":17,"correct":18},"B","监理单位（项目）负责人",false,{"key":20,"text":21,"correct":18},"C","施工单位（项目）负责人",{"key":23,"text":24,"correct":18},"D","质量监督机构","本题考查的是单位工程竣工验收。单位工程完工后，施工单位应自行组织有关人员进行检查评定，并向建设单位提交工程验收报告。建设单位收到工程验收报告后，应由建设单位（项目）负责人（选项A）组织施工（含分包单位）（选项C）、设计、监理（选项B）等单位（项目）负责人进行单位（子单位）工程验收。质量监督机构（选项D）只是代表政府行使监督职责，不是竣工验收的组织人。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]