[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120099":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1120099,790,1,"单选题","建筑工程施工项目质量控制内容包括：①工序质量、②检验批质量、③分项工程质量、④分部工程质量、⑤单位工程质量，下列控制顺序中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→②→③→④→⑤",true,{"key":16,"text":17,"correct":18},"B","②→①→③→⑤→④",false,{"key":20,"text":21,"correct":18},"C","②→①→④→③→⑤",{"key":23,"text":24,"correct":18},"D","⑤→④→③→②→①","本题考查的是单位工程竣工验收。建筑工程质量验收应划分为单位（子单位）工程.分部（子分部）工程、分项工程和检验批。每个检验批由若干个施工工序构成，施工项目的质量控制过程是从工序质量到检验批、分项工程质量、分部工程质量、单位工程质量的系统控制过程。因此正确的控制顺序为①→②→③→④→⑤，选项A正确。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]