[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120098":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1120098,790,1,"单选题","某大楼主体结构分部工程质量验收合格，则下列说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该分部工程所含分项工程质量必定合格",false,{"key":16,"text":17,"correct":14},"B","该分部工程质量控制资料必定完整",{"key":19,"text":20,"correct":14},"C","该分部工程观感质量验收必定符合要求",{"key":22,"text":23,"correct":24},"D","该单位工程质量验收必定合格",true,"本题考查的是分部工程的质量验收。分部工程质量验收合格规定：（1）所含分项工程的质量均应验收合格；（选项A正确）（2）质量控制资料应完整；（选项B正确）（3）有关安全、节能、环境保护和主要使用功能的抽样检验结果应符合相应规定；（4）观感质量应符合要求。（选项C正确）但是，单位工程质量验收合格的前提之一是所有分部工程验收合格，但主体分部工程验收合格，并不一定得出单位工程质量验收必定合格的结论。故选项D说法错误。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]