[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120040":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1120040,790,1,"单选题","某工程在施工过程中因不可抗力造成如下损失：永久工程损坏修复费用 16万元，承包人受伤人员医药费 4 万元，施工机具损失 6 万元，应发包人要求赶工发生费用 2 万元，停工期间应发包人要求承包人清理现场费用 4 万元。承包人及时向项目监理机构提出索赔申请，并附有相关证明材料。根据《建设工程施工合同（示范文本）》，项目监理机构应批准的索赔金额为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","24",{"key":19,"text":20,"correct":21},"C","22",true,{"key":23,"text":24,"correct":14},"D","32","索赔金额=16+2+4（清理现场费用）=22 万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建筑工程实务","建筑工程",0]